Which information do I have to enter in section C.8?

In this section kindly include information only in line with relevant partners and activities. Please note that a line is created per partner and activity belonging to a WP where the partners has budget. Do not take into consideration the amount displayed, because that is the total amount of the WP and not of the activity. Please do not take into consideration the last amount of the page.

Not relevant lines may remain empty. Please check Step # 11 of the Synergie guide for further information regarding the information to be included in concerned lines.

Category : Completing the application form (for lead partners)

Which information do I have to enter in section C.6?

In this section kindly include information only in line with relevant partners and activities to be implemented outside the MED area.

Activities to be implemented by partners outside the MED area should not be included. Not relevant lines may remain empty.

Category : Completing the application form (for lead partners)

In the section - Enter main elements - / – budget - which information should be completed in the field - Cost by units -?

The fields of this section should not be completed. The budget should only be completed via the Enter main elements -> Work Plan -> Work Package -> Expenditure forecast. No sub-categories should be created, nor cost units.

Please refer to Step # 11 of Synergie guide, last paragraph, for further information.

Category : Completing the application form (for lead partners)

In a testing project, activities - Testing - and - Simulating - do not appear in the drop-down list?

Those activities are considered “pilot activities” and you have to tick on “Is a pilot activity” in order to make them appear on the list.

Category : Completing the application form (for lead partners)

In the section - Enter Main Elements -, tab - Indicators -, information appears as a consequence of entering the project contribution to Programme Output Indicators. Which information should be completed?

In the section – Enter main elements -, tab – Indicators -, no information should be completed. Those comment boxes cannot be removed from the system but they do not have to be filled in in the framework of the Interreg MED Programme.

Category : Completing the application form (for lead partners)

The field - Description of the Work Package - appears twice in the system, without being replicated (in Enter main elements - Working Plan and in the main index – C.5 Work Plan). Which field should be completed?

In the section – Enter main elements – / – Working Plan -, the field regarding the description of the work package (as well as the field – Supply -) should not be completed. Those comment boxes cannot be removed from the system but they do not have to be filled in in the framework of the Interreg MED Programme. The description of the Work Packages should only be completed once, via the index (C.5 Work plan, from C.5.3 to C.5.20, choosing only the WPs relevant for your project type), with a limitation of 2000 character maximum per each WP description.

Category : Completing the application form (for lead partners)

What does - Supply - mean, in the work plan?

This comment box can not be removed from the system but it does not have to be filled in in the framework of the Interreg MED Programme. Please do not take into consideration this comment.

Category : Completing the application form (for lead partners)

May any activity be targeted to different target groups?

Only one target group can be selected for each activity, please chose the main target group for each activity. If there are other target groups involved please include it in the comment. Kindly remember that all the target groups selected would be used in section “C.2.2 Target groups” (see Step # 12 of the Synergie guide), so please be sure that that all relevant target groups have been selected at least one along the Application Form.

Category : Completing the application form (for lead partners)

According to the Programme Manual, the budget has to be entered by semester. How can I do that on Synergie?

Due to a dysfunction of the online monitoring tool this information will not be requested in the first call for modular projects.

Category : Completing the application form (for lead partners)

When I create the activities they start on January 1st, 2014, how can I change that?

Before creating the activities you must change the sarting and ending date of your proposal. If, despite, this you cannot create activities, kindly send an e-mail to programme_med@regionpaca.fr writing “Synergie” and “dates”in the object of your mail , and including in the text of your message the following information: acronym of the proposal.

Category : Completing the application form (for lead partners)